2. Answer each of the following independent questions and show all relevant computations on the answer sheet. (25%)
(2) TSMC has budgeted construction overhead for August of $435,000 for fixed costs. Actual costs for the month totaled for $450,000 for fixed. Allocated fixed overhead totaled $430,000. The company tracks each item in an overhead control account before allocations are made to individual jobs. The fixed overhead spending variance for August was $15,000 unfavorable for fixed.
Required:
Make journal entries to record the actual costs incurred as well as the variances for August.